Tunnel Oberau

Location: Oberau - Germany
Customer: Marti GmBH
Working years: 2017 - 2018
Project information: Expansion of the B2 federal road with the bypass of the village of Oberau.

The route runs between the junctions Oberau-Nord and Oberau-Süd under the Mühlberg, the Gießenbachtal and the Kirchbichl.

Construction of 2 x 2,800 m long tunnels in conventional method.
Supplied equipments: Provision of 2 complete Trains composed of Formwork, Curing, Reinforcement and Service Gantries.
Niches and Connection collars.
Additional Services: Machine installation , Machine Transformations ,