For more than a year, KERN has been supplying Lot H-53 of the Brenner Base Tunnel, the world’s longest underground railway connection, with state-of-the-art tunnel formworks, logistic equipment, and special gantries across multiple sections of the project.
Among our key contributions:
-
Fully automated hydrostatic shutters for the main tunnel tubes
-
Complete machinery for all enlargement sections, including parament and vault formworks, reinforcement gantries, and logistic system (Multi Service Gantry - MSG with Pallet Carriage System)
-
Heavy-duty vault formwork for the emergency stop tunnel
-
Special collar formworks for various tunnel intersections
-
Cross-passage formworks for multiple cross-sections and different block lengths
-
Lifting and rotation platforms for tunnel shutters with 30-ton SWL
-
Reinforcement and working gantries
-
K-Vertex lifting system with up to 100-ton SWL capacity
-
Process simulations and digital method statements produced by our subsidiary, KERN Lab
-
Complete on-site service, including initial assembly and acceptance tests, on-site machine transformations, and tight project coordination
-
Two sets of KERN’s K-ONE casting system for main tunnel shutters
-
Modular MAXIMO wall formworks from PERI
-
KERN’s MSG-01 applied across multiple new jobsite locations
We are particularly proud for the successful introduction of our first REVO tunnel formwork gantry, designed and produced using a newly developed modular machine-building methodology.
What makes REVO special:
-
Significantly reduced assembly times, with full on-site setup in just 7 days
-
Increased overall jobsite productivity and minimized impact on project schedules
-
Modular design allows easy transformation for different tunnel geometries or block lengths
-
At H-53, two REVO gantries and five sets of modular formwork have been supplied for the complete tunnel enlargement
-
The formwork system is designed so that no rails are required
All machines and solutions have been fully designed and engineered by KERN and produced with our long-standing partners.
We extend our sincere thanks to all our engineering and manufacturing teams, suppliers, and partners for their remarkable performance. We also thank our customer for the excellent collaboration over the past months and years. Meeting the demands of this ambitious project has been a tremendous achievement.